Marcos approves P26.78-billion budget for Samal-Davao bridge, pushes completion to 2029

The Samal Island-Davao City Connector now costs P3.74 billion more and is due by November 30, 2029, about three years later than first planned.

DavaoNews Desk · based on reporting by Edge DavaoTue, Nov 17, 7:30 AM
Photo: Edge Davao

President Ferdinand R. Marcos Jr. has approved a higher budget and a later completion date for the Samal Island-Davao City Connector (SIDC) Project. The cost rises from P23.04 billion to P26.78 billion, and the target finish moves to November 30, 2029, Edge Davao reported.

According to the Presidential Communications Office (PCO), the changes were approved at the 12th Economy and Development Council (EDC) meeting, which Marcos led in Malacañang on November 11, 2026. That date was also the bridge's original completion target, so the new deadline adds slightly more than three years.

The proposed restructuring first went through the Investment Coordination Committee-Cabinet Committee (ICC-CC), co-chaired by Finance Secretary Frederick D. Go. The committee approved it and then endorsed it to the EDC for final approval.

The President also directed the Department of Public Works and Highways (DPWH) to resolve funding and implementation concerns so the project stays on track, the PCO said. He repeated that the government will prioritise major projects in energy, transportation, flood control, education and social protection.

The project began under former President Rodrigo Duterte. It is a 3.98-kilometre, four-lane, toll-free bridge across Pakiputan Strait. It will link R. Castillo-Daang Maharlika Road in Davao City to the Samal Circumferential Road in the Island Garden City of Samal (IGaCoS). The bridge is designed to carry about 25,000 vehicles a day.

Most of the funding comes from an Official Development Assistance loan from the Chinese government worth 2.34 billion renminbi, or about P17.39 billion. A progress report released on November 13 put the project at 65.42 percent complete.

Once the bridge opens, it is expected to make it easier for residents, commuters, tourists and businesses to travel between the two cities. It should also improve access to jobs, schools, markets, tourist destinations and essential services.

Why it matters for Davao

People who travel between Davao City and Samal will have to wait about three more years for the toll-free bridge. The project is expected to ease commutes and open better access to jobs, services and tourism.

This article was written by the DavaoNews desk with AI assistance, using reporting by Edge Davao. Facts come from the original report, which we credit and link below. Our editorial policy

Read the original at Edge Davao

How does this story make you feel?

Be the first to respond

Share this story

Sign in to get a personal share link and earn community points when readers open it.

Discussion (0)

Sign in with Google to join the discussion.

Sign in to comment

No comments yet. Start the conversation.