Davao City sets aside ₱88.7 million bond for waste-to-energy project
The City Council tapped the 2025 surplus to post a performance bond required by the Department of Energy after the city won a slot in the first national waste-to-energy auction.
Davao City has set aside ₱88.7 million for a performance bond demanded by the Department of Energy (DOE), after the city emerged as a winning bidder in the national government's first waste-to-energy (WTE) auction, according to PravdaReport.
The City Council approved the amount on November 17, 2026 through Supplemental Budget No. 3, drawing from the city's 2025 surplus. The money is coursed through the Land Bank of the Philippines and serves as a guarantee that the city will carry out the project. Under DOE rules, winners of the October 13 Special Green Energy Auction must submit the bond and other requirements within 30 days of the notice of award, or face disqualification and loss of their bid bonds.
Councilor Diosdado Mahipus Jr. abstained from the vote, saying he did not yet fully understand the green auction and the details of the project. Mayor Sebastian Duterte has named Atty. Tristan Dwight Domingo as WTE project manager to handle compliance and implementation.
The council also passed an ordinance adopting the bidding documents for building the facility, which is funded by a grant from the Government of Japan under an Exchange of Notes signed on March 20, 2018. The City Legal Office said Crown Agents Japan Limited will serve as the employer procuring the engineering, procurement and construction works as well as operation and maintenance services. The office added that the ordinance does not appropriate city funds or create new financial obligations, since construction is grant-funded.
Councilor Danilo Dayanghirang said the city collects about 800 tons of garbage a day, and its new sanitary landfill in Barangay New Carmen is expected to be full in about five years. The old landfill was closed and ordered rehabilitated after a May 20 trash slide killed two people.
The planned plant in Barangay Biao Escuela is designed to handle 600 tons of waste daily and produce 13 megawatts of electricity, 11 megawatts of which would go to the grid. The DOE has set December 31, 2028 for mechanical completion and December 31, 2029 for the start of power delivery.
The project still lacks an environmental clearance. The Environmental Management Bureau (EMB)-Davao is reviewing its environmental impact statement, prepared by a consultant hired by Jica. Regional Director Alnulfo Alvarez said the plant must have equipment to capture and treat dioxins and furans, along with round-the-clock emissions monitoring.
The environmental group Interfacing Development Interventions for Sustainability (Idis) opposes the project, arguing that incineration runs counter to a circular economy and that toxic emissions can build up in the human body even when they stay within regulatory limits.
Why it matters for Davao
With the city collecting about 800 tons of garbage daily and the New Carmen landfill projected to fill up in five years, the plant is a central part of the city's waste plan, though its emissions remain under regulatory review and contested by environmental advocates.
This article was written by the DavaoNews desk with AI assistance, using reporting by PravdaReport. Facts come from the original report, which we credit and link below. Our editorial policy